Breach of the main sewer line of the Be’er Sheva leading from the WWTP, in a short period of 24 hours, a steel pipe with a diameter of 42" and a length of 109 m was laid down as a special project, in which an overhead water line crossing Nahal Olim was replaced ..

 

In order to perform the special work, were required:

  • 5 excavators
  • 1 bulldozer
  • 1 backhoe
  • 2 welding teams
  • A pumping system that includes 3 pumps in order to carry out bypass of waterflow
  • Installation of site lighting
  • 30 employees and managers worked on the project.
  • The laydown and execution of the works was done in an exceptional short period of only 24 hours!

A special task that the Oron Group has met with great success.

 

 

 